CY1: Security thinking: assets, threats and risk

Lesson 4 of 5 · reading 15–25 minutes; practice and project time is on the module page

Risk: deciding what to fix first

🎯You'll be able to

Rate risks by likelihood and impact, keep a risk register, and choose a treatment for each risk.

🏠The everyday picture

A family can't fix everything in an old house at once. A loose wire near the children's room comes before a squeaky door, even though the door annoys everyone more often.

📘What it really is

📝A worked example

Input: three risks for AarogyaDesk. Password guessing on the login page, a stolen backup on an unencrypted USB drive, the server failing on a weekday.

Steps:

  1. Rate them. Password guessing: likelihood 4, impact 4, score 16. Stolen backup: 2 and 5, score 10. Server failure: 3 and 3, score 9.
  2. Choose treatments. Guessing: reduce with lockouts and multi-factor login. Backup: reduce with encryption. Server: reduce with a tested restore and accept a few hours' downtime.
  3. Name owners and review dates.

Expected output: a register of three rows, ordered by score, each with a treatment and an owner. These ratings are illustrative.

🌍Where it's used

📝Case scenario

A small accounting firm listed 40 risks and tried to fix them all in one month, finishing none. When it ranked them and fixed the top five first, backups and multi-factor login were in place within two weeks.

🖱️Try it

Rate these four risks for a clinic from 1 to 5 for likelihood and impact: a phishing email to reception, a power cut, a lost staff laptop, a flaw in the booking search. Success: they're ordered, and you can explain your top choice in one sentence.

⚠️Common mistakes

🛠️For your project

Project 1's findings use the same idea: each one has a severity, and the report puts the most serious first.

✅Quick check

A risk has likelihood 2 and impact 5. Another has likelihood 4 and impact 4. Which comes first by score?

Show the answer

The second: 16 against 10.

What does accepting a risk require?

Show the answer

A named owner with authority, a written reason and a review date.

← PreviousThreat modelling: thinking ahead